Project Description

Travis Electric Company has been an integral part of maintaining the facilities at Hoeganaes for over 20 years. The Plant has expanded to over 12 times its original size with Travis Electric at the helm, providing electrical expertise in all major expansions. Some of the upgrades and expansion projects include doubling the size of the existing arc furnace, upgrades to the band furnaces, installation of 4 new band furnaces, more than doubling the size of the 161kV substation by removing a 25MVA transformer and installing 50MVA and 18MVA transformers, electrical installation for a new hydrogen recovery plant, as well as electrical upgrades for the shipping facilities, which tripled in size.